Dam breach reconstruction of the Blažňov pond caused by extreme hydrological event
Příspěvek v časopisu
Permanent link
http://hdl.handle.net/20.500.11956/161815Identifiers
Collections
- GEOBIBLINE - Fulltexts [10555]
Issue Date
2010Keywords (Czech)
geologieKeywords (English)
floods, flood reconstruction, dam breach, hydrodynamic model, HEC-RASThis article deals with the reconstruction of the dam breach of the Blažňov pond and consequent flood wave progress in the riverbed of the small brook. The dam breach occurred at the night from 28. 3. 2006-29. 3. 2006. The cause of the breach was above au increased inflow to the pond as a result of heavy rainfall together with intensive snowmelt. The earth-fill dam of the pond was in the time of breach corrupted by water rodents. The flood wave progressed through the brook valley with the length of 0.7 km. Consequently it fulfilled the Podolí pond, which is situated below the Blažňov pond. Podolí pond was in this time empty and the flood wave was completely transformed there. Measurements of the wave course and cross-sections through valley were made by total geodetic station. An extraction of flood sediments were carned out three locations and their textures were analyzed. The reason was a description of the sedimentation process in the reach. For the modeling of the flood extremity and flood extent the hydrodynamic model HEC-RAS was applied (Hydrologic Engineering Centre - River Analysis System)